petter 发表于 2009-10-27 17:05

transformers overload test

      Transformers for switch mode power supply units are tested in the complete power supply unit
or in the complete equipment. Test loads are applied to the output of the power supply unit.
      A linear transformer or a ferro-resonant transformer has each secondary winding loaded in
turn, with any other secondaries loaded between zero and their specified maxima to result in
the maximum heating effect.
      The output of a switch mode power supply unit is loaded to result in the maximum heating
effect in the transformer.
Where an overload cannot occur or is unlikely to create a hazard, the above tests are not
made.
       对于最后一句:过载或危险不可能发生,就不用做上面的测试大家是怎么理解的。
    例如一个Adapter做LVD的话大多数人说不要,TVU sud一般也不要,但是UL一般都要做,但是在我公司有变压器的都要做,为此我都提过几次意见了,不知道大家对此标准时怎么理解的。

yangzhiqiou 发表于 2009-10-27 17:33

UL的测试是比较严格,

Alexsong 发表于 2009-10-27 20:38

从标准上来讲开关电源产品只需在输出端做过载即可, 目前TUV,ITS也都是这样做的. 但UL则要求在输出端和变压器次级都需要拉载, 为此我还专门问过UL的PDE, 也没有明确的答复, 只是说是其内部要求.

faige2006 发表于 2009-10-28 10:29

UL講的transformer overload和output overload是不同的. UL每次witness, 這兩個測試是必做的. 不知TUV和ITS witness是否也做?

petter 发表于 2009-10-28 10:53

TVU 莱茵的是经过二极管后拉过载,而且温升曲线要拉成三段,要不然不给过。UL的不是很清楚

weldo 发表于 2009-10-28 10:59

请问是在变压器副边就直接接二极管吗?

petter 发表于 2009-10-28 11:12

拉过载用直流负载,一般都在变压器次级输出经整流二极管后面拉一组线出来接到负载,先正常跑一段温升,跑的差不多直了加负载,跑直了继续加,第三次加的时候直接加到Adapter shutdown,就可以得到三段曲线

jianfie 发表于 2009-10-28 11:44

UL对变压器的测试较严,transformer overload必做的

隐形 发表于 2009-10-29 08:36

TUV 做65是要这样做Transformer的过载,且曲线要有曲度,但是95的话,现在也基本没有这样要求了。

martin_chiu 发表于 2009-10-29 10:42

您所寫的部分是由Annex C 擷取出來的,
對於除UL 的認證單位, 若是transformer 二次側能符合SELV, 則output overload and transformer overload 是可以互相替代的

但是, UL 認為 output overload 不一定能替代 transformer overload