PDSH 1022 Short circuit and overload protection
http://decisions.iecee.org/icons/ecblank.gif PDSH 1022
Short circuit and overload protection
15.3.2
61558-1(ed.1);am1 & 61558-1(ed.2);am1
Standard(s):
IEC 61558-1
All editions
Subclause(s):
15.3.2
No. Year
PDSH
1022 2010
Category: SAFE Developed by: ETF5
OSM/LUM
Subject:
Short circuit and overload
protection
Key words:
- Fuse current
- Overloading test
- Overload current
To be approved at the 49th
CTL Plenary Meeting, in 2012
Question:
During the overloading test on the transformer according to § 15.3.2 the temperature of the windings and
their resistance increase and consequently the overload current decreases. Has the fuse current be
readjusted to the original overload current during the test or no adjustment has to be made?
Decision:
The fuse current has to be kept constant during the test.